Published On
10/01/2024🚘 WEEKLY ROAD WORKS UPDATE
As we head into the new year we are continuing to roll out a sustained program of works to deliver road improvements and maintenance. Some of the road works this week include:
🚧 Pothole filling at Berkeley Vale, Chittaway Bay, Gunderman, Holgate, Kulnura, Matcham, Rocky Point, Spencer, Summerland Point, Tuggerawong, Umina Beach, Wyongah
🚧 Road grading at Greengrove (Mangrove Creek Rd), Kulnura (Williams Rd, Parana Rd), Mangrove Mountain (Parukala Rd), Umina Beach (Various Lanes)
🚧 Road rehabilitation at Erina (Erina Valley Rd)
🚧 Road shoulder maintenance at Spencer (Wisemans Ferry Rd)
🚧 Road pavement works at Warnervale (Albert Warner Dr)
DID YOU KNOW?
Road repairs are prioritised by level of risk and traffic volumes, with higher traffic roads generally requiring attention first.
For workflow and cost efficiencies, repair work may be undertaken on several roads in the same suburb around a priority site.
Scheduling of road repairs requires a flexible approach as new issues can be identified or reported at any time, and weather can impact which works are able to be carried out – which is why plans are adjusted each week.
To see what road projects are planned for this financial year, view our interactive capital works map, or refer to Council’s annual operational plan.
To report or enquire about specific road maintenance or safety concerns:
• Online: Go to our online Customer Service Centre. Lodging your request this way ensures it is registered in Council's system and will provide you with a reference number of which you'll be able to track if necessary.
• Telephone: Please contact our Customer Service Team on 02 4306 7900
📷 PHOTO: Heavy patching at Yarramalong, Yarramalong Rd